California Davis-Bacon prevailing wages

Federal Davis-Bacon rates apply to construction projects in California that receive federal funding or federal assistance. These rates are specific to each county and construction type—building, residential, heavy, or highway—so you’ll need to match your project’s location and scope to the correct wage determination. California also has its own prevailing-wage system, managed by the Department of Industrial Relations (DIR), but PrevailMap focuses solely on federal Davis-Bacon rates, not DIR rates. When a project falls under both federal and state prevailing-wage laws, contractors must pay the higher rate for each classification. Weekly certified payroll (form WH-347) is required on federal jobs, including a signed statement of compliance. Always verify the rates against the wage determination attached to your contract.

Federal Davis-Bacon coverage in California kicks in when a construction contract exceeds $2,000 on a federal project — a military base, a VA hospital — or a federally-assisted one, such as HUD-funded housing or FAA airport work. When a job carries both federal and state funding, common in infrastructure and affordable housing, you cross-check the federal wage determination against California’s DIR rates for the same county and work type and pay the higher rate for each classification: if the DIR rate is higher it controls, and if the federal rate is higher it does.

To find the right determination, match the project’s county and construction type — say, Alameda County heavy construction — then apply those rates to the weekly certified payroll (WH-347) with its signed statement of compliance. Missing the higher-of-two rule or skipping certified payroll can mean back wages, penalties, or trouble bidding future federal work, and because the federal and state labor agencies enforce separately, it’s worth confirming DIR’s rates yourself on any mixed-funded job.

New to Davis-Bacon? How federal prevailing wage works →

Determinations
28
Counties covered
58
Construction types
3
Rates last verified
August 13, 2026

Cached daily from SAM.gov: Building 15 · Residential 11 · Heavy 2

28 current determinations, grouped by construction type. Each link is one wage determination and the counties it covers.

Building construction

Residential construction

Heavy construction

Davis-Bacon prevailing wage: common questions

Do I need certified payroll for a federal job?
Yes. For Davis-Bacon covered contracts, you must submit weekly certified payroll (Form WH-347) with a signed Statement of Compliance. This applies to both prime contractors and subcontractors.
What is the difference between base rate and fringe?
The base rate is the hourly cash wage. The fringe is benefits (e.g., health insurance, retirement). The total prevailing wage is base + fringe. You can pay it as all cash, all benefits, or a mix.
What does a * in the fringe column mean?
A '*' means the fringe rate is defined in a collective bargaining agreement (CBA) or other source—not zero. You must obtain the actual rate from the CBA; the WD alone doesn’t show it.
How often do wage determinations change?
Wage determinations (WDs) are updated periodically, sometimes annually. Always use the WD revision number specified in your contract—even if newer versions exist.
Which wage determination applies to my job?
Use the WD incorporated into your contract. It’s based on the project’s location (usually county) and construction type (e.g., building, highway). Check the contract or ask the awarding agency.
Do these federal rates replace my state's prevailing wage?
No. Federal Davis-Bacon rates apply only to federally funded projects. State prevailing wage laws may still apply to other work. Always check both requirements.